The Chief Information Officer (CIO) wants to implement a redundant server location to which the production server images can be moved within 48 hours and services can be quickly restored, in case of a catastrophic failure of the primary datacenter’s HVAC. Which of the following can be implemented?
A. Cold site B. Load balancing C. Warm site D. Hot site
Answer: C
Explanation: Warm sites provide computer systems and compatible media capabilities. If a warm site is used, administrators and other staff will need to install and configure systems to resume operations. For most organizations, a warm site could be a remote office, a leased facility, or another organization with which yours has a reciprocal agreement.