PMP Question 115

Late in the project cycle, it was discovered that some of the project human resources needed to have been trained on a specific methodology. Ideally, where should these training needs have first been documented? A. Staffing management planB. In the procurement contractC. In the project scope statementD. In the company HR policy Show Answer A.