PMP Question 72

The Risk Management plan will usually contain the definitions of risk probability and impact. Which of the following has the highest impact (negative) on a project? A. A rating of 1.1 on the impact scaleB. A rating of 0.8 on the impact scaleC. A rating of 0 on the impact scaleD. A rating of 0.1