PMP Question 189

The selection of life cycle for the project, the processes to be applied to each phase, and the results of the tailoring by the project management team are usually found in the: A. Project scope statementB. Project management planC. Project scheduleD. Project charter Show Answer B. Project management plan

Tagged with 
project charter project management plan Project schedule Project Scope Statement
 