PMP Question 62

You have met with your project sponsor and have been told that the project MUST be completed by the end of the year, no exceptions. This should be included in the project scope statement as a: A. Project ConstraintB. Project BoundaryC. Project Acceptance CriteriaD. Project Assumption Show Answer A. Project Constraint

Tagged with 
Project Acceptance Criteria Project Assumption Project Boundary Project Constraint
 