PMP Question 63

A project manager drew up a resource histogram. On plotting the histogram, he found that some bars extended beyond the maximum available hours. What does this usually signify? A. This means that the resources on those bars are being underutilized.B. This means that a resource optimization strategy needs to be appliedC. This means that the