PMP Question 38

You just found out that a major subcontractor for your project consistently provides deliverables late. The subcontractor approaches you and asks you to continue accepting late deliverables in exchange for a decrease in project costs. This offer is an example of: A. ForcingB. SmoothingC. ConfrontingD. Compromise Show Answer D. Compromise