PMP Question 83

Which of these is accurate regarding the Develop Schedule process? A. Schedules are optimized such that all non-critical activities have a zero total float.B. The critical path method is a schedule network analysis technique that is performed using the schedule modelC. Schedule compression shortens the project schedule while changing the project scopeD. Schedule network analysis