PMP Question 116

A project is contracted as a Cost-Plus-Incentive-Fee (CPIF) type of contract. The project is negotiated such that if the final costs are less than expected costs, the sharing formula for cost savings is 75:25. The targeted cost is US$ 100,000 with an 8% incentive fee on the targeted cost. If the project comes in at