PMP Question 43

Why are the approved change requests input to the Direct and Manage Project Work process? A. Approved change requests may be rejected by the project team during the Direct and Manage Project Work process.B. Approved change requests are implemented by the project team during the Direct and Manage Project Work process.C. Approved change requests are