PMP Question 181

A contract change control system should include: A. Vendor contact information, tracking systems, and approval levels necessary for authorizing changesB. Paperwork, tracking systems, dispute resolution procedures, and approval levels necessary for authorizing changesC. Information database, dispute resolution procedures, and approval levels necessary for authorizing changesD. Tracking systems, legal ramifications for certain actions, and approval levels