PMP Question 98 ( PMBOK 6th edition )

A project manager has scheduled technical training for her project team members in order to increase their skills. During which of the following processes these training will be delivered to the team members?

A. Manage Quality
B. Acquire Resources
C. Develop Team
D. Plan Resource Management

C. Develop Team