PMP Question 96

While performing an audit on a project run by another project manager, a certified PMP, you find that project processes have not been followed, and that company procurement policies have been repeatedly violated. What do you do?

A. Develop a plan to deal with the associated problems.
B. Ask the project manager to explain why these things have happened.
C. Notify the appropriate management immediately.
D. File a complaint with PMI

C. Notify the appropriate management immediately.