PMP Question 89

How would you calculate your EAC if the ETC work will be performed at the budgeted rate?

A. EAC = BAC/CPI
B. EAC= BAC-EV
C. EAC = AC + BAC – EV
D. EAC=(BAC-EV)*CPI

C. EAC = AC + BAC – EV