PMP Question 85

During a project status review meeting, some of the project team members have raised a concern over the complexity of the project performance information reporting requirements. The project team is of the view that the work performance data should be sufficient for reporting. Which of the following is the best response that should be given to team members?

A. The work performance information is necessary for the conversion of the resisting project stakeholders to supportive project stakeholders.
B. Compliance to the PMBOK requires transforming the work performance data to work performance information.
C. This is a non-negotiable requirement and the project manager is not required to convince the team.
D. The work performance data alone is not sufficient for effective decision making.

D. The work performance data alone is not sufficient for effective decision making.