Jane is estimating the overall expected cost of a new ERP system deployment project using the actual costs of an earlier similar ERP system deployment project as the basis for the cost. This is what type of estimating?

A. Analogous
B. Bottom-up
C. Expert Judgment
D. Parametric

A. Analogous