PMP Question 79

You are in the middle of a risk assessment meeting with key stakeholders, customers and project team leaders. While identifying and assessing risks, you have realized that two key stakeholders are overemphasizing the impact of a risk. What is the BEST step you must take to avoid unfairness or bias when assessing risks?

A. Implement assumptions analysis to explore the validity of assumptions
B. Develop a risk response strategy to eliminate threats
C. Perform qualitative risk analysis to identify risk attitudes
D. Perform sensitivity analysis to establish which risks have the most impact on the project

C. Perform qualitative risk analysis to identify risk attitudes