PMP Question 72

The Risk Management plan will usually contain the definitions of risk probability and impact. Which of the following has the highest impact (negative) on a project?

A. A rating of 1.1 on the impact scale
B. A rating of 0.8 on the impact scale
C. A rating of 0 on the impact scale
D. A rating of 0.1 on the impact scale

B. A rating of 0.8 on the impact scale