PMP Question 71

Jane is currently developing her project’s stakeholder register. She wants to identify the internal and external parties that are involved in the project. Which of the following documents can provide this information to Jane ?

A. Scope management plan
B. Project charter
C. Stakeholder management plan
D. Project management plan

B. Project charter