PMP Question 70 ( PMBOK 6th edition )

Which of the following processes goes beyond the distribution of relevant information and seeks to ensure that the information being communicated to project stakeholders has been appropriately generated, as well as received and understood?

A. Manage Communications
B. Control Communications
C. Manage Stakeholder Engagement
D. Monitor Stakeholder Engagement

A. Manage Communications