PMP Question 7

Peter is managing a software development project for the first time. He is facing issues with scheduling meetings with the senior project managers at the company as they are extremely busy with their current assignments. Peter needs to understand what went right and wrong on previous similar projects so that he can manage his project better. In this situation, what should Peter do?

A. Review the project’s business case for details.
B. Request key stakeholders to help schedule these coaching meetings.
C. Review lessons learned from the past similar projects.
D. Review the project charter for details.

C. Review lessons learned from the past similar projects.