PMP Question 68

A project manager analyzed the project’s communication requirements and decided that 10 out of the 30 stakeholders in the project would only need voicemail updates of certain information. This type of communication method is called:

A. Push communication
B. Pull communication
C. Interactive communication
D. On-demand communication

A. Push communication