You have met with your project sponsor and have been told that the project MUST be completed by the end of the year, no exceptions. This should be included in the project scope statement as a:

A. Project Constraint
B. Project Boundary
C. Project Acceptance Criteria
D. Project Assumption

A. Project Constraint