You are managing a project for your company constructing an office complex in another country. The construction work on 2 of the buildings is complete and is ready for move-in. However, the construction foreman informs you that a fee must be paid to a local government agency in order to be issued an occupancy permit for all new construction in that country. What should you do?

A. Pay the fee.
B. Ask your legal department if this is legal.
C. Notify project stakeholders that you have been asked to pay a bribe.
D. Do not pay the fee.

A. Pay the fee.