PMP Question 42 ( PMBOK 6th edition )

A project manager is working on the Manage Quality phase of a project. He is looking for an iterative means to improve quality and eliminate activities that don’t add value. Which of the following will help him do this?

A. Quality control measurements
B. Quality checklist
C. Continuous process improvement
D. Team rewards

C. Continuous process improvement