PMP Question 38

You just found out that a major subcontractor for your project consistently provides deliverables late. The subcontractor approaches you and asks you to continue accepting late deliverables in exchange for a decrease in project costs. This offer is an example of:

A. Forcing
B. Smoothing
C. Confronting
D. Compromise

D. Compromise