PMP Question 28

A software development project team has determined the best way to mitigate the risk of not having the computational resources to complete all bug testing on schedule is to add 3 more servers to the test bed. However, the network may not have enough capacity to handle the extra load of those three servers and could fail. This type of risk is called a ___________________ risk.

A. Secondary
B. Simulation
C. Bottleneck
D. Hidden

A. Secondary