PMP Question 27

The most recent analysis of Microcorp’s new fabrication facility renovation shows a CPI value of less than 1.0 What does this indicate?

A. The cost has overrun estimates.
B. The cost has underrun estimates.
C. The project is running ahead of schedule.
D. The schedule has slipped.

A. The cost has overrun estimates.