PMP Question 23

As part of stakeholder analysis, a project manager drew up a power / interest grid. The project manager identified that a stakeholder could be classified low on the “interest” scale, and also as low on the “power” scale. What strategy should be used for such a stakeholder?

A. Monitor
B. Manage closely
C. Keep informed
D. Keep satisfied

A. Monitor