PMP Question 197

A project manager uses a Power / Interest grid to identify stakeholders in the project and to manage their expectations. Identify which of the following statements is wrong in the context of a Power / Interest grid.

A. Stakeholders with lower power and lower interest need to be monitored.
B. Stakeholders with higher power and lower interest need to kept satisfied.
C. Stakeholders with lower power and higher interest need to be kept informed
D. Stakeholders with higher power and higher interest need the least attention.

D. Stakeholders with higher power and higher interest need the least attention.