PMP Question 192

As part of the Risk Response planning for your project, you are trying to come up with a strategy to deal with negative risks or threats. In order to eliminate the impact of a particular risk, you relax the objective that is in jeopardy by extending the project schedule. This is an example of

A. Transference
B. Mitigation
C. Avoidance
D. Postponement

C. Avoidance