PMP Question 191

Organizational process assets are key inputs to the Manage Stakeholder Engagement process. The key elements of the organizational process assets utilized during this process are organizational communication requirements, issue management procedures and the change control procedures. Which of the following is also a key organizational process asset that must be considered during this process?

A. Process audit procedures
B. Human resource policies
C. Historical information about previous projects
D. Project document templates

C. Historical information about previous projects