You are reviewing the responses to an RFP issued by your company and realize that a major requirement was not included in the RFP that was released. By chance, however, one of the bidders included that requirement in their response. What is the best course of action?

A. Award the contract to that bidder.
B. Revise and reissue the RFP.
C. Select the bid that included the requirement.
D. Cancel the RFP.

B. Revise and reissue the RFP.