PMP Question 176

The project manager in charge of a new credit card software project has asked the product manager to create a checklist to assist with the identification of risks. A risk checklist can be created from which of the following sources?

A. Agreement templates
B. Earned value measurements
C. Project Management Information System
D. The lowest level of the Risk Breakdown Structure

D. The lowest level of the Risk Breakdown Structure