PMP Question 174 ( PMBOK 6th edition )

You have just returned from the weekly change control board meeting where you presented the requested changes to the employee move project. You had five change requests approved, however one rejected request. These are outputs of what process?

A. Control Quality
B. Control Scope
C. Monitor Risks
D. Perform Integrated Change Control

D. Perform Integrated Change Control