PMP Question 173

The key difference between Validate Scope and Control Quality is:

A. Validate Scope is concerned with meeting the quality standards specified.
B. Validate Scope is concerned with the acceptance of deliverables.
C. Validate Scope does not apply in projects that have been cancelled.
D. Validate Scope can never be performed in parallel with quality control.

B. Validate Scope is concerned with the acceptance of deliverables.