PMP Question 172

Which of the following best describes the Validate Scope process?

A. Validating that the project quality requirements have been met
B. Controlling changes to the scope of the project
C. Obtaining stakeholders’ formal acceptance of the project deliverables
D. Validating that all of the project’s objectives have been met

C. Obtaining stakeholders’ formal acceptance of the project deliverables