PMP Question 171

Jane is the project manager of large project. During the Determine Budget process, she identifies that contingency reserves need to be made for unplanned but potentially required changes that could result from realized risks identified in the risk register. Which of the following is true about reserves?

A. Management Reserves are not a part of project cost baseline, but will be included in the total budget for the project
B. Contingency Reserves are not a part of project cost baseline, but will be included in the total budget for the project
C. Both the Management Reserves and the Contingency Reserves are not part of project cost baseline, and they are also not included in the total budget for the project
D. Both the Management Reserves and the Contingency Reserves are not part of project cost baseline, but they are included in the total budget for the project

A. Management Reserves are not a part of project cost baseline, but will be included in the total budget for the project