PMP Question 163

You have assembled a group of subject matter experts (SMEs) to perform an exercise where they are going to complete a probability and impact matrix chart. You and your team are still in what process group?

A. Risk
B. Monitor and Controlling
C. Quantitative Analysis
D. Planning

D. Planning