PMP Question 162

During a work breakdown structure meeting you have decomposed the deliverables into work packages and created your WBS dictionary. However, you now want to decompose the work packages to assist you in estimating, executing and control the project. These decomposed work packages are called?

A. Work Packages can’t be decomposed into smaller units
B. Activities
C. Milestones
D. Control Accounts

B. Activities