PMP Question 161

A project manager is considering risk in a project. When does risk come into play in a project?

A. During the SWOT (strengths, weaknesses, opportunities, and threats) analysis.
B. During the Identify Risks phase.
C. As soon as the Plan Risk Management phase begins
D. As soon as a project is conceived

D. As soon as a project is conceived