PMP Question 154

As project manager, you scheduled a status update meeting. During the meeting, a problem developed and the group discussed it. The day after the meeting, Kevin approached you and expressed his concern that the problem was not really resolved. After thinking about it, he felt that his concerns were still valid and should be addressed. What conflict resolution method was likely used at the status meeting?

A. Smoothing
B. Forcing
C. Withdrawal
D. Collaboration

A. Smoothing