PMP Question 152

The project management plan can best be described as:

A. A list of tasks, activities, durations and resources in a software program (e.g., Microsoft Project)
B. Coordinating changes across the entire project
C. Integrating and coordinating all project plans to create a consistent, coherent document
D. Integrating and coordinating all project documents and stakeholder expectations

C. Integrating and coordinating all project plans to create a consistent, coherent document