In an ongoing project, the project sponsor and a manager of the performing organization are having conflicts. What would be your comment on this situation?

A. The project manager needs to step in and handle the stakeholders’ expectations. The stakeholders may have different objectives and interests in the project.
B. The project manager needs to step in and handle the stakeholders’ expectations. All stakeholders are supposed to have the same objectives and interests in a project.
C. The project manager should resolve in favor of the project sponsor since he is providing the funds for the project.
D. The project manager should resolve in favor of the manager of the performing organization since they are executing the project and need to be kept in good books.

A. The project manager needs to step in and handle the stakeholders’ expectations. The stakeholders may have different objectives and interests in the project.