PMP Question 140

You are defining the schedule activities for your project and identifying deliverables at the lowest level in the Work Breakdown Structure (WBS). You find that there is insufficient definition of the project scope to decompose a branch of the WBS down to the work package level. You now look at using the last component in that branch of the WBS to develop a high-level project schedule for that component. Such a planning component is called:

A. A planning packet
B. Control system
C. A planning package
D. Control element

C. A planning package