PMP Question 139

A project manager wishes to illustrate the connections between the work that needs to be done and the project team members. According to the PMBOK, the resulting document would be called:

A. Responsibility Assignment Matrix (RAM)
B. Resource Planning Chart (RPC)
C. Task Assignment Model (TAM)
D. Resource Assignment Chart (RAC)

A. Responsibility Assignment Matrix (RAM)