The WBS structure can be created in a number of forms except which of the following?

A. Using work packages as the second level of decomposition, with the project deliverables inserted at the third level.
B. Using major deliverables as the second level of decomposition.
C. Using phases of the project life cycle as the second level of decomposition, with the product and project deliverables inserted at the third level.
D. Using subcomponents which may be developed by organizations outside the project team, such as contracted work.

A. Using work packages as the second level of decomposition, with the project deliverables inserted at the third level.