PMP Question 128

The Identify Stakeholders process has four inputs. Three of them are project charter, enterprise environmental factors and organizational process assets. What is the fourth one?

A. Procurement documents
B. Stakeholder register
C. Stakeholder engagement matrix
D. Stakeholder management plan

A. Procurement documents