PMP Question 122

Which of the following is incorrect regarding a bidders conference?

A. Questions from each seller should be handled confidentially and not shared with other sellers.
B. No bidders should receive preferential treatment, even if they are part of the company’s existing list of approved suppliers.
C. Bidders conferences should not involve individual face-to-face meetings
D. All prospective sellers should be allowed to have a common understanding of the procurement.

A. Questions from each seller should be handled confidentially and not shared with other sellers.