Late in the project cycle, it was discovered that some of the project human resources needed to have been trained on a specific methodology. Ideally, where should these training needs have first been documented?

A. Staffing management plan
B. In the procurement contract
C. In the project scope statement
D. In the company HR policy

A. Staffing management plan